PVA Spiringen (UR): first installation


Thursday, 14. August 2025

The first solar modules were successfully installed last week at the Sidenplangg alpine PV plant in Spiringen (UR), a project by energieUri and aventron.
The goal of putting at least 10 % of the plant into operation by the end of 2025 is therefore rapidly approaching. In order to achieve the target, around 250 solar module tables, one of the two transformer stations and the majority of the service lines must be completed by the end of the year.